Brandon Valley School District

                                            "Home of the Lynx”

 

 

 

 

            Valley Springs Elementary School

 

 

 

 

Five-Year Plan (2009-2014)

 

 

 

Compiled by:

 Tanya Czepull, Principal/Curriculum Director

 

 

 


Valley Springs Elementary

Enrollment Projections

 

Predictions with Growth

 

VSE

2009-10

2010-11

2011-12

2012-13

2013-14

5th grade

15

27

21

35 (2 sec.)

35 (2 sec.)

4th grade

28

21

34 (2 sec.)

35 (2 sec.)

35 (2 sec.)

3rd grade

21

34 (2 sec.)

35 (2 sec.)

35 (2 sec.)

35 (2 sec.)

2nd grade

34 (2 sec.)

35 (2 sec.)

35 (2 sec.)

35 (2 sec.)

35 (2 sec.)

1st grade

35 (2 sec.)

35 (2 sec.)

35 (2 sec.)

36 (2 sec.)

40 (2 sec.)

Kindergarten

38 (2 sec.)

38 (2 sec.)

38 (2 sec.)

40 (2 sec.)

40 (2 sec.)

TOTAL:

171

190

198

216

220

 

 

0% Growth

 

VSE

2009-10

2010-11

2011-12

2012-13

2013-14

 

5th grade

14

27

21

35 (2 sec.)

37 (2 sec.)

 

4th grade

27

21

35 (2 sec.)

37 (2 sec.)

34 (2 sec.)

 

3rd grade

21

35 (2 sec.)

37 (2 sec.)

34 (2 sec.)

34 (2 sec.)

 

2nd grade

35 (2 sec.)

37 (2 sec.)

34 (2 sec.)

34 (2 sec.)

34 (2 sec.)

 

1st grade

37 (2 sec.)

34 (2 sec.)

34 (2 sec.)

34 (2 sec.)

34 (2 sec.)

 

Kindergarten

34 (2 sec.)

34 (2 sec.)

34 (2 sec.)

34 (2 sec.)

34 (2 sec.)

 

TOTAL:

168

188

195

208

207

 

 

 

If our enrollment continues to stay steady or increase minimally, we will become a two section school for all grade levels.  This will mean we will need to add 3 full time grade level teachers by 2012.  The success or failure of the Kindergarten Academy Pilot program will be a deciding factor in whether or not Valley Springs Elementary will become a two section school.

 

 

 

 

 

 

 

 

 

          

2009-2010

 

Staffing Needs and Requests: 

A.    Transfer 3rd Grade teacher to 2nd Grade

 

  B.  Math Specialist (District)..................................................................................... $ 45,000

          Rationale: Due to high emphasis on Math in NCLB, RTI and our NCA goals,

          teachers would benefit from the opportunity to consult with a math specialist.

          The math specialist would also facilitate small group lessons with students

          struggling in the math content area.  In addition the math specialist would

          help coordinate and provide professional development opportunities for teachers.

            The math specialist would split time between all elementary buildings in the district.

 

  C.  Full-time Educational Assistant……………………………………….................................... $ 25,000

          Rationale: Due to the high needs of the Kindergarten Academy students,

          a full time EA is requested to help with management  and small group

          instruction, similar to the Jr. Kind. EA position.  This EA would also help

            facilitate the RTI program for grades K-5.

 

Curriculum Needs:

A.    Social Studies Adoption..................................................................................... $ 14,000

B.     Everyday Math (K-6 consumables)...................................................................... $ 11,000

C.     Success Maker Upgrade..................................................................................... $ 20,000

D.    STAR Early Literacy........................................................................................... $  1,500

 

Equipment Needs:

A.    Replacement student desks................................................................................ $   3,500

B.     Amplification system (1)................................................................................... $   1,500

C.     Teacher replacement computers (3).................................................................... $   3,000

D.    Replace Computer lab....................................................................................... $ 30,000

E.     2 Smartboards/Projectors.................................................................................. $   6,000

F.      Senteo Responders........................................................................................... $   4,000

 

Physical Plant Needs:

A.    Exterior storage room for gymnasium and library………………………………………………… $ 42,000

B.     Fire door for Speech Room................................................................................... $1,000

C.     Handwashing sink for kitchen............................................................................... $1,000

D.    New lighting in library.......................................................................................... $5,000

E.     Suspended ceilings in 1922 rooms....................................................................... $20,000

F.      Countertop in Educational Assistant Room............................................................. $1,000

G.    Replace Stair Railings in 1922 Building................................................................... $5,000

 

 

 

 

 

 

2010-2011

 

Staffing Needs and Requests:

A.    Add 1 FTE....................................................................................................... $ 45,000

Rationale: Increased enrollment, add 3rd grade section

 

Curriculum Needs:

A.    Science Adoption.............................................................................................. $ 20,000

 

Equipment Needs:

A.    Amplification System........................................................................................ $   1,500

B.     Teacher replacement computers (3).................................................................... $   3,000

C.     Classroom Furniture for New Teacher................................................................. $   2,000

D.    Classroom set desks/chairs................................................................................ $   4,000

E.     3 Smartboards/Projectors (1st Grade/New 3rd)...................................................... $   9,000

F.      Senteo Responders........................................................................................... $   4,000

 

Physical Plant Needs:

A.  Carpet replacement.......................................................................................... $ 42,000

B.  Deep Sink upstairs for Science lab work.............................................................. $   5,000

C.     Refinish/replace double doors between lunchroom and lobby................................. $10,000

D.    New carpet and ceiling in Educational Assistant room.............................................. $2,000

E.     Update bathrooms in 1922 building................................................................... $100,000

 

 

 

 

2011-2012

 

Staffing Needs and Requests:

A.    Add 1 FTE........................................................................................................ $ 45,000

Rationale: Increased enrollment, add 4th grade section

 

Curriculum Needs:

  A.  Fine Arts Adoption........................................................................................... $   7,000

  B.  Everyday Math (K-6).......................................................................................... $ 11,000

 

Equipment Needs:

  A.  (1) Amplification system.................................................................................... $  1,500

  B.  (3) Teacher Replacement Computers.................................................................... $  3,000

  C.  Classroom Furniture for New Teacher.................................................................. $  2,000

  D.  Smartboard/Projector (Kind./Music/New 4th)........................................................ $  9,000

  E.  Classroom desks/chairs...................................................................................... $  4,000

 

Physical Plant Needs:

  A.  Playground Resurfacing..................................................................................... $ 30,000

 

 

 

2012-2013

 

Staffing Needs and Requests:

A.     District Technology Integrationist..................................................................... $  45,000

Rationale: Due to the emphasis on technology and21st Century Skills,

a Technology integrationist is necessary to help teachers integrate technology

effectively into their day-to-day instruction.

 

B.      Add 1 FTE...................................................................................................... $ 45,000

Rationale: Increased enrollment, add 5th grade section

 

Curriculum Needs:

  A.  PE/Health......................................................................................................... $  7,000

       B.  Everyday Math (K-6)..................................................................................... $ 13,000

 

Equipment Needs:

  A.  (1) Amplification System.................................................................................... $  1,500

  B.  (3) Teacher Replacement Computers.................................................................... $  3,000

  C.  Classroom Furniture for New Teacher.................................................................. $  2,000

  D.  Smartboard (New 5th)........................................................................................ $  3,000

  E.  Furniture for New 5th.......................................................................................... $  2,000

 

Physical Plant Needs:

 

 

 

 

 

 

2013-2014

 

Staffing Needs and Requests:

 

Curriculum Needs:

  A.  Reading/English Adoption................................................................................. $ 40,000

  B.  Everyday Math (K-6).......................................................................................... $ 13,000

 

Equipment Needs:

  A. (1) Amplification System.................................................................................... $   1,500

  B. (3) Teacher Replacement Computers.................................................................... $   3,000

 

 

Physical Plant Needs: