Brandon Valley High School Addition 22-23


  • BVHS Classroom Addition Planned Utility Interruption - Power Outage
    • The Brandon Valley High School facility will be closed and unavailable Monday, November 21 - Wednesday, November 23, 2022
    • BVHS Power wiil be shut down on Monday, November 21, 2022 @ 7:30 a.m.
    • BVHS Power will be restored on Wednesday, November 23, 2022 @ 5:00 p.m.
    • BVHS will utilize Distance Learning during the shut down.
    • For additional information regarding BVHS Academic and Operational Items regarding the shut down period CLICK HERE
  • BVHS Classroom Addition Project Priorities
    • General Classrooms
    • Ground Floor Special Education
    • Science Lab Classrooms
    • Maximize Land Usage / Upgrade East Facility Face / Minimize Impact to Parking
  • BVHS Addition Schedule - Overview of Important Dates
    • May 2022 - Parking Lot Construction Begins
      • Parking Lot Construction to be completed by August 2022
    • Wednesday, June 1, 2022 - BVHS Classroom Addition Construction Begins
    • Friday, June 16, 2023 - Substantial Completion